Interconnection Standards
You can interconnect rooftop solar to Alabama Power's grid by submitting an application through PowerClerk and ensuring approval before installation; you'll need to comply with Southern Company's Interconnection Policy and Alabama Power's Technical Requirements Guidebook. You can apply a rate rider (RGB) to maintain grid backup power and may sell excess energy through Rate PAE (systems under 100kW) or Rate CPE (100kW and larger). Check local zoning rules and your homeowner's association before proceeding, and consider pairing solar with battery storage to address inconsistent sunlight.
Systems must comply with Southern Company's DER Interconnection Policy, Alabama Power's Technical Interconnection Requirements Guidebook, and the Alabama Power DER Interconnection Process; applications are submitted via PowerClerk and must be approved before installation begins. Customers interconnecting to the grid are subject to rate rider RGB for backup and maintenance power, and systems under 100kW can sell excess energy via Rate PAE while larger systems use Rate CPE. The scope of required system impact studies and any additional equipment studies are determined jointly with the utility and may involve extra review if energy storage is incorporated.
Alabama lacks statewide interconnection standards; Southern Company (Alabama Power's parent) maintains a DER parallel-operation policy without explicit system-size thresholds for review levels. System impact studies and optional interconnection equipment studies are determined jointly between the DER owner and utility; energy storage integration may trigger additional study requirements. Customers apply via PowerClerk and must comply with technical guidebooks; rate rider RGB applies to all interconnected generators, while excess-energy purchases are structured through Rate PAE (under 100kW) and Rate CPE (100kW+).
Program details
- Program ID
- 22626
- Last updated
- 1/2/2026
Eligibility
- Technologies
- solar photovoltaics wind (all) biomass fuel cells using non-renewable fuels wind (small) fuel cells using renewable fuels lithium-ion
Program summary
Alabama does not have statewide interconnection standards.
Southern Company, the parent company of Alabama Power Company, does have a policy on operation of distributed energy resources (DER) in parallel with the distribution system.
The policy does not give explicit information on system size limits in relation to levels of review. The scope of any required system impact study is determined jointly by the DER owner and the utility. Following the system impact study, an interconnection equipment study may also be required. Incorporation of energy storage systems may require additional study.
Contact & resources
- Contact email
- g2apcrenewables@southernco.com
- Additional resources
Please verify current program details with the administering agency before making any financial decisions.