NH Solar/Wind Permitting Standards

Standards for Municipal Small Wind Regulations and Model Ordinance

AI summary · 7/12/2026

New Hampshire law prevents your municipality from blocking small wind turbines up to 100 kW or imposing unreasonable restrictions—setbacks cannot exceed 150% of your system height, and noise limits must follow state standards. To install, you'll need a building permit, must comply with FAA regulations, and should expect notification of nearby neighbors as part of the application process.

You can market small wind systems (up to 100 kW) in New Hampshire with confidence that municipalities cannot prohibit them outright or impose excessive setbacks (capped at 150% of system height) or design standards beyond state and federal codes. Installations must meet FAA requirements and applicable airport zoning, and your customer's application will trigger neighbor notification but follows a standardized municipal review process.

This 2008 law constrains municipal authority over small wind (≤100 kW) by prohibiting outright bans and capping setbacks at 150% of system height unless a municipality adopts stricter regulations via zoning variance. The state provides a model ordinance (no binding authority) to guide local permitting; your jurisdiction must comply with the baseline standards but may customize procedures for application review and abandonment enforcement at owner expense.

Program details

Program ID
4676
Last updated
5/26/2023

Eligibility

Sectors
commercial industrial investor-owned utility local government nonprofit municipal utilities residential cooperative utilities schools state government federal government tribal government agricultural institutional
Technologies
wind (all) wind (small)

Program summary

In July 2008, New Hampshire enacted legislation designed to prevent municipalities from adopting ordinances or regulations that place unreasonable limits on or hinder the performance of wind energy systems up to 100 kilowatts (kW) in capacity. Such wind turbines must be used primarily to produce energy for on-site consumption. The law identifies several possible restrictions that would be considered unreasonable:

  • The outright prohibition of small wind turbines (i.e., wind turbines up to 100 kW) in all districts of a municipality.
  • Generic height restrictions that do not specifically address the allowable tower height or system height of small wind turbines.
  • Property boundary setback requirements greater than 150% of the system height. Smaller setback requirements are permitted by the adoption of a regulation or through a zoning variance, but the standard setback is set at 150% of the system height if a municipality declines to adopt a specific setback requirement.
  • Setting maximum noise limits than specified by site evaluation committee rules -- measured at the site property line -- or not allowing the limit to be exceeded during short-term events such as power outages or wind storms.
  • Setting structural or design standards that exceed the applicable state, federal, or international building or electrical codes or laws.

The law requires wind turbines to comply with all Federal Aviation Administration (FAA) regulations and applicable airport zoning regulations. It also includes rules and processes for the removal of out-of-service or abandoned turbines (at the owner’s expense). Finally, it includes a requirement to notify immediate neighbors upon application for a building permit.

The law also required the New Hampshire Office of Energy and Planning to issue a technical bulletin and develop a model ordinance to help guide local municipalities to follow the standards as they develop their own ordinances. Municipalities may change the model ordinance as appropriate. Major components of the model ordinance include a procedure for reviewing proposed small wind turbines, standards for reviewing applications for small wind turbines, and abandonment procedures.*

For a catalog of recent planning legislation and amendments to state statutes, click here.

* This model ordinance was designed to provide guidance to local governments that want to develop their own siting rules for wind turbines. While it was developed as part of a cooperative effort involving stakeholders and governmental entities, the model itself has no legal or regulatory authority. The standards are required, however.

Contact & resources

Please verify current program details with the administering agency before making any financial decisions.