Maine's interconnection rules let you connect small renewable energy systems (solar, wind, geothermal, or other distributed generation) to the grid through a streamlined process based on your system's size. For inverter-based systems up to 25 kW, you pay a $100 fee and follow the simplest approval path; larger systems face higher fees ($2–$3 per kW) and more detailed review, but certified equipment that meets IEEE Standard 1547 and UL 1741 can avoid additional controls. Apply through your utility, and systems over 50 kW require a Maine Licensed Professional Engineer's design review.

You can offer interconnection services for distributed generation across all technologies and customer types in Maine under a tiered framework that scales with system size. Level 1 (≤25 kW) and Level 2 (≤2 MW) projects have straightforward technical screens and modest fees; Level 3 (≤10 MW non-exporting) and Level 4 (larger systems) require more detailed studies and site-specific utility upgrade costs borne by the applicant. Ensure equipment is certified by a Nationally Recognized Testing Laboratory and meets IEEE 1547 and UL 1741 standards; insurance requirements range from none (inverter-based ≤1 MW) to $2–$3 million depending on technology and capacity.

Maine's interconnection procedures, adopted by the PUC in January 2010 and last updated in 2020, create four tiered review levels based on system size and export capability, with fees ranging from $100 (Level 1) to $3,000 plus study costs (Level 4). The framework applies to all distribution generation technologies across residential, commercial, industrial, government, school, and nonprofit sectors; inverter-based systems dominate lower tiers, while larger non-inverter-based facilities face higher insurance requirements ($3 million for >5 MW). Federal entities use a modified standard form agreement and self-insure under the Antideficiency Act; all systems must use certified equipment tested by NRTLs and comply with IEEE Standard 1547 and UL 1741.

Program details

Program ID
3917
Last updated
1/3/2026

Eligibility

Sectors
commercial industrial local government nonprofit residential schools state government federal government
Technologies
geothermal electric solar thermal electric solar photovoltaics wind (all) biomass hydroelectric municipal solid waste tidal wave wind (small) other distributed generation technologies

Program summary

The Maine Public Utility Commission (PUC) adopted interconnection procedures in January 2010; the rules were last updated in 2020. These rules apply to all transmission and distribution utilities operating in the state and apply to all distribution generation (not just renewables). Maine's interconnection procedures, based in part on the Interstate Renewable Energy Council's. 2006 Model Interconnection Procedures,* identify four different tiers with corresponding technical screens. These are:

  • Level 1: Small certified generating, inverter-based facilities 25 kilowatts (kW) or less;
  • Level 2: Certified facilities 2 megawatts (MW) or less;
  • Level 3: Non-exporting, certified facilities 10 MW or less;
  • Level 4: Any generating facility that does not qualify for the aforementioned levels of review, and are not subject to jurisdiction of the Federal Energy Regulatory Commission (FERC).

Fees and Requirements

Fees for interconnection requests increase with each level. A Level 1 request must submit a $100 fee; a Level 2 request must submit a fee of $100 plus $2/kW of generator capacity; a Level 3 request must submit $100 plus $3/kW of generator capacity; and a Level 4 request must submit an application fee of $3,000 (including a $500 fee for any application changes). In addition, Level 4 applicants are responsible for fees associated with the interconnection study, as well as any utility upgrades required to accommodate the requested interconnection. Project designs require review and approval by a Maine Licensed Professional Engineer for generators greater than 50 kW.

Equipment Standards

The PUC specifies that IEEE Standard 1547 (“Standard for Interconnecting Distributed Resources with Electrical Power Systems”) and UL 1741 ("Inverters, Converters, and Controllers for Use in Independent Power Systems") as the technical standards of evaluation. Systems are considered to be certified for interconnection if the components have been tested and listed by a Nationally Recognized Testing Laboratory (NRTL) and if they meet the definition of certification under FERC Order 2006 for Small Generator Interconnection Procedures, according to these standards. Additional controls (such as external disconnect switches) are not permitted when facilities use certified equipment.

Insurance Requirements

Depending on the size of the small generator facility, insurance requirements differ. No insurance is required for inverter-based facilities with a rated capacity of 1 MW or less. Inverter-based facilities with a rated capacity exceeding 2 MW but less than or equal to 5 MW must carry liability insurance with coverage of at least $1 million. Facilities with rated capacity greater than 5 MW must carry liability insurance with coverage of at least $2 million. Insurance coverage for non-inverter-based generating facilities ranges from no insurance (50 kW or less) to $3 million (for facilities greater than 5 MW).

Government Standard Form Interconnection Agreement

In May 2014, the PUC adopted a standard form interconnection agreement for use exclusively by federal government entities. The agreement is a modified version of the standard form interconnection agreement, with changes made to comply with the Antideficiency Act, the Federal Tort Claims Act, and the Automatic Payment of Judgments Act. Under this agreement, federal government entities will self-insure and are not required to carry insurance. The applicable form can be found under "Forms for Utilities," after clicking here.

* IREC updated its model interconnection procedures in 2013. The 2013 model is available on IREC's website.

The information provided here covers several important classification criteria and provides a brief summary of the procedures. Consult the actual rule for official definitions, additional restrictions, and comprehensive information on the technical screens.

Contact & resources

Please verify current program details with the administering agency before making any financial decisions.