NM Interconnection
AI summary · 11/15/2026

New Mexico's interconnection rules let you connect a solar, wind, or other generating system to the grid if your utility is regulated by the PRC (municipal utilities are exempt). Systems up to 25 kW export and 50 kW nameplate use a simplified process, with an application fee of $150 for systems up to 25 kW. You'll also need a redundant external disconnect and a mutual indemnification agreement with the utility, so check with your utility to start.

Review path depends on size: Simplified for up to 25 kW export and 50 kW nameplate, Fast Track up to 5 MW, Full Study above 5 MW to 10 MW, and Case Specific Study above 10 MW. Systems must meet NEC, IEEE, and UL standards, include a redundant external disconnect (visibly marked and utility-lockable above 10 kW), and have a mutual indemnification agreement. Application fees are $150 up to 25 kW, $300 above 25 kW to 100 kW, and $300 plus $1 per kW above 100 kW, with lower fees for non-export systems, and insurance may be required for larger systems.

Adopted by the PRC in July 2008 and updated in 2022, Rule 569 covers qualifying facilities up to 80 MW and Rule 568 simplifies interconnection for renewable and CHP systems up to 10 MW. The 2022 update uses export capacity in some cases to better reflect energy storage impacts. All PRC-jurisdictional utilities must offer net metering and comply, while municipal utilities are exempt, and costs are borne by applicants through size-based fees, with small utilities under 50,000 customers able to charge reasonable consulting fees above 10 kW. The rules apply to residential, commercial, industrial, nonprofit, school, and government customers.

Program details

Program ID
3038
Last updated
6/6/2024

Eligibility

Sectors
commercial industrial local government nonprofit residential schools state government federal government
Technologies
geothermal electric solar thermal electric solar photovoltaics wind (all) biomass hydroelectric municipal solid waste combined heat & power fuel cells using non-renewable fuels landfill gas wind (small) hydroelectric (small) fuel cells using renewable fuels other distributed generation technologies microturbines lithium-ion

Program summary

The Public Regulation Commission (PRC) adopted revised standards and procedures for the interconnection of generating facilities in New Mexico in July 2008.

Rule 569 applies to all qualifying facilities (QFs) under the federal Public Utility Regulatory Policies Act, which generally includes all renewable energy systems and combined heat and power (CHP) systems up to 80 megawatts (MW) in capacity.

Rule 568 applies to renewable energy systems and CHP systems up to 10 MW in capacity. The purpose of Rule 568 is to simplify the interconnection requirements for QFs up to 10 MW and to encourage the use of small-scale, customer-owned renewables or alternative energy resources.

New Mexico adopted updated interconnection standards in 2022. New Mexico's new rules in some cases use "export capacity" rather than total capacity to measure system size to better reflect the impact of energy storage.

Incentives

All utilities subject to PRC jurisdiction must offer net metering and comply with these standards. (Municipal utilities, which are not regulated by the commission, are exempt.)

System Capacity Requirements

Interconnection applications will generally follow this review path:

  • Systems up to 25 kilowatts (kW) in export capacity and 50 kW in nameplate capacity are eligible for the "Simplified Interconnection Process," which includes simplified applications.
  • Systems up to 5 MW are eligible for the "Fast Track Process," which might include supplemental review.
  • Systems greater than 5 MW and up to 10 MW must follow the "Full Interconnection Study Process."
  • Systems greater than 10 MW must follow the "Case Specific Study Process."

Process

All systems must comply with all relevant local and national standards (including the NEC, IEEE and UL standards) and meet any additional requirements approved by the PRC. A redundant external disconnect device is required for all interconnected systems. For systems greater than 10 kW, the disconnect switch must be visibly marked and accessible to and lockable by the utility.

The PRC may require the owner of a generating facility with a rated capacity of up to 250 kW to obtain general liability insurance prior to connecting with a utility if the utility provides a sufficient reason for doing so. A utility may directly and independently require owners of systems greater than 250 kW to provide proof of insurance, with reasonable limits not to exceed $1,000,000, or other reasonable evidence of financial responsibility. A mutual indemnification agreement between the customer and the utility is required.

Interconnected customers must pay an application fee that varies according to the size of the system. Systems up to 25 kW must pay $150; systems greater than 25 kW and up to 100 kW must pay $300; and systems greater 100 kW must pay $300 plus $1 per kW. If a system is non-export only, it has a fee of $150 if below 100 kW, or $300 if above 100 kW. In addition to these fees, a small utility with fewer than 50,000 customers may charge reasonable consulting fees for systems greater than 10 kW.

Contact & resources

Please verify current program details with the administering agency before making any financial decisions.