Town of Kill Devil Hills - Wind Energy Systems Ordinance
If you want to install a small wind turbine in Kill Devil Hills, you'll need to obtain a zoning permit from the town planning board. Your system is limited to 10 kilowatts with a tower height of 80 feet maximum (92 feet total with rotor), and it must be set back from property lines by at least its full height, plus 250 feet from certain highways and 100 feet from neighboring turbines. You'll need a professional engineer to seal the structural plans, and your system must meet a 60-decibel noise limit and keep a neutral appearance with no signage or lighting (except FAA-required equipment).
Wind systems installed in Kill Devil Hills must comply with strict specifications: maximum 10 kW capacity, 80-foot tower height, self-supporting monopole or lattice tower design, 250-foot highway setback, and under-60-decibel noise performance. You must work with a North Carolina licensed Professional Engineer for structural certification, ensure the site is at least one acre, and comply with all local, state, and national codes. When a system reaches end-of-life, it must be removed within 120 days.
Kill Devil Hills' October 2007 wind ordinance establishes a permitting framework administered by the town planning board. The program regulates residential, commercial, agricultural, nonprofit, school, institutional, and local government wind installations through a zoning permit process, with technical requirements including maximum 10 kW capacity, monopole/lattice towers, professional engineer certification, 60-decibel noise compliance, and specific setback distances (property line = tower height, highways = 250 feet, turbine-to-turbine = 100 feet). Decommissioning must occur within 120 days of system failure or retirement.
Program details
- Program ID
- 2860
- Last updated
- 8/15/2023
Eligibility
- Sectors
- commercial industrial local government nonprofit residential schools agricultural institutional
- Technologies
- wind (all) wind (small)
Program summary
In October 2007, the town of Kill Devil Hills adopted an ordinance to regulate the use of wind-energy systems. The ordinance directs any individual or organization wishing to install a wind-energy system to obtain a zoning permit from the town planning board.
Size Requirements: Wind turbine towers are restricted to a height of 80 feet with a maximum rotor size of 23 feet in diameter. The combined height of the system must not exceed 92 feet above finished grade. All wind systems are limited to a rated power of 10 kilowatts (kW).
Visual Appearance: Towers and rotor blades must maintain a neutral color and must not create a visual distraction from the ground. Wind systems must also remain free from signage and artificial lighting, except that which is required by the Federal Aviation Administration (FAA). No type of communications antennae or array may be installed or connected to the wind turbine.
Setbacks: The site for wind system installations must be at least one acre. Wind systems must be set back from all property lines by at least the distance of their height. They must also maintain a distance of at least 250 feet from certain highways and 100 feet from each other.
Installation and Noise Requirements: Wind turbine towers must be a self-supporting tubular tower (monopole); self-supporting lattice tower; or a guyed-lattice typed with a minimum guy radius of 50% of the tower height and a maximum radius of 90% of its height. The base of the tower must be secured in a way that prevents climbing. All systems must maintain a noise level of less than 60 decibels in keeping with town code. A North Carolina licensed Professional Engineer must seal all structural plans and all components of the system must conform to relevant local, state and national codes. At such time the turbine is no longer functioning the tower shall be removed within 120 days.