VA Interconnection
AI summary · 11/15/2026

If you want to connect solar or another small system to the grid in Virginia and net meter, you must get approval from your utility before installing; residential systems up to 20 kW qualify, and the utility is deemed to approve if it doesn't respond within 30 days. Expect to carry at least $100,000 in liability insurance for systems up to 10 kW ($300,000 above that), possibly pay up to $50 for an inverter inspection on inverter systems over 10 kW, and reimburse the utility for any grid upgrades your system requires. Your utility may also require a manual external disconnect switch, so check its net metering tariff.

Net-metered systems must meet NEC, IEEE 1547 and UL standards, and customers must notify and get approval from the utility and energy service provider before installation (30 days for residential, 60 days for nonresidential before automatic approval). Non-net-metered projects follow SCC three-level review using standard SCC forms: Level 1 up to 500 kW with a $100 fee, Level 2 certified facilities up to 2 MW with a $500 fee, and Level 3 for larger facilities with a deposit and possible feasibility, impact and facilities studies, and Levels 2 and 3 require a signed interconnection agreement before operation. Liability insurance scales with size, from $100,000 per occurrence at 10 kW or less up to $2 million for systems above 500 kW through 2 MW, and the utility decides whether an external disconnect switch is required.

Virginia has two tracks: net-metered systems under 20 VAC 5-315-40 (residential up to 20 kW, non-residential up to 1,000 kW, subject to the utility's 1% of peak load cap) and non-net-metered systems under SCC procedures effective July 2009 based on the FERC SGIP, applying to investor-owned utilities, municipal utilities and cooperatives. The SCC procedures use three review tiers with escalating fees, IEEE 1547 as the technical standard, UL 1741 and NEC lab certification, aggregate-capacity evaluation for multi-device sites, and a dispute process through the SCC Division of Energy Regulation, third-party resolution, or a formal complaint. The 2018 revisions removed the 20 MW cap, added energy storage rules, queue numbers and utility queue reporting, revised the material modification definition, and increased the Level 3 study deposit; the rules cover all sectors and technologies, and costs of interconnection upgrades fall on the customer-generator.

Program details

Program ID
808
Last updated
5/31/2024

Eligibility

Sectors
commercial industrial local government nonprofit residential schools state government federal government agricultural
Technologies
geothermal electric solar thermal electric solar photovoltaics wind (all) biomass hydroelectric municipal solid waste tidal wave wind (small) lithium-ion

Program summary

Virginia has two interconnection standards: one for net-metered systems and one for systems that are not net-metered.

Interconnection for Net-Metered Systems

Customer-generators that net meter must comply with the interconnection rules within the regulations governing net metering (20 VAC 5-315-40). These rules apply to residential customers with generation facilities up to 20 kW in capacity and non-residential systems up to 1,000 kW in capacity. Utilities that have already enrolled 1% of their peak load for the previous year are not required to allow additional customers to net meter. More information is available under DSIRE Virginia net metering post.

Customer-generators with systems that meet the major national safety and equipment standards [National Electrical Code (NEC), Institute of Electrical and Electronic Engineers (IEEE) Standard 1547 (July 2003), and Underwriters Laboratories (UL)] are not required to install any additional safety equipment. However, a utility’s net metering tariff may require that customer-generators install a manual, external disconnect switch that complies with national safety requirements and is certified by a licensed electrician.

Customer-generators must notify and receive approval from the electric distribution company and the energy service provider prior to installation of the generation facility. The distribution company has 30 days after the date of notification to determine if the requirements are met for interconnection. The application for interconnection is considered automatically approved if the electric utility does not respond within 30 days for residential customers and 60 days for nonresidential customers.

Customer-generators may be required to pay up to $50 for an inverter inspection for inverter-based systems that are greater than 10 KW. In addition, customer-generators must reimburse the utility for its cost to modify any facilities or equipment needed to accommodate the interconnection with respect public safety, power quality, and reliability of the system.

Customer-generators with interconnected systems that do not exceed 10 kW in rated capacity must have at least $100,000 in liability insurance. Customer-generators with systems greater than 10 kW must have at least $300,000 in coverage.

Interconnection for Other Systems**

In May 2009, Virginia’s State Corporation Commission (SCC) adopted interconnection procedures for systems that are not net-metered. These rules, which took effect July 1, 2009, apply to all electric utilities -- investor-owned utilities, municipal utilities and electric cooperatives -- operating in Virginia. Prior to installation, the Interconnection Customer must insure compliance with all local, state and federal laws and regulations, including applicable permitting and easements.

The FERC Small Generator Interconnection Procedure (SGIP) rules provide the basis for these regulations. The interconnection procedures set three tiers of review for interconnection requests for all eligible technologies and systems up to 20 MW, including those interconnecting to both the distribution grid and the transmission grid (if an interconnection is subject to state jurisdiction). The three tiers are:

• Level 1: Small generating facilities no larger than 500 kW;

• Level 2: Certified facilities no larger than 2 MW that do not qualify for the Level 1 process;

• Level 3: Facilities no larger than 20 MW not qualifying for the Level 1 or Level 2 process.

Fees for interconnection requests increase with each Level. A Level 1 request must submit $100 fee; a Level 2 request must submit $500 fee; and a Level 3 requests must submit a deposit of $1000 or 50% of the estimated cost of the feasibility study (whichever is less).

The process for each level differs as well; in general Level 1 requests require an evaluation and no additional studies. Level 2 requests require an initial review and possibly a supplemental review and/or modifications to either the small generating facility or the utility facilities. Level 3 requests may include a scoping meeting (which may be waived), a feasibility study (which may be waived), system impact study, and facilities study. Level 2 and 3 both require a signed Small Generator Interconnection Agreement before the systems may begin operation. The forms for requests and agreements are standard SCC determined forms.

The SCC specifies IEEE Standard 1547 (“Standard for Interconnecting Distributed Resources with Electrical Power Systems”) as the technical standard of evaluation. Systems are considered to be lab-certified if the components have been evaluated as compliant with UL 1741 and the National Electric Code (NEC).

Interconnection requests that include multiple energy production devices located on one site with a single point of interconnection will be evaluated on the aggregate capacity of all systems. Interconnection request for systems wishing to increase capacity shall be evaluated on total new capacity.

Regardless of the size or tier in which the facility is evaluated, it is the utility's discretion whether or not an external disconnect switch is required.

Depending on the size of the small generator facility, insurance requirements differ. Facilities with rated capacity 10 kW or less must carry liability insurance of at least $100,000 per occurrence. Facilities with rated capacity exceeding 10 kW but less than or equal to 500 kW must carry liability insurance with coverage of at least $300,000 for each occurrence. Facilities with rated capacity greater than 500 kW but less than or equal to 2 MW must carry liability insurance with coverage of at least $2 million per occurrence. Insurance coverage for facilities with rated capacity greater than 2 MW will be determined on a case-by-case basis, depending on the size of the installation and potential risk of system damage.

Another important aspect to the SCC Interconnection procedures for non-net metered systems is that they stipulate a dispute resolution process. After written notification of the dispute, the parties may seek assistance from the SCC's Division of Energy Regulation, where it will be handled as an informal complaint, or they may seek third-party dispute resolution in which costs are shared equally. If the prior attempts fail, parties may file a formal complaint with the SCC.

It should be noted that these regulations do not apply to net metering customers although, in practice, the process and requirements detailed for Level 1 requests mirror the interconnection process for net metered systems.

The SCC revised the interconnection rules for non-net metered systems in 2018, adopting several changes. The changes removed the 20 MW size cap for interconnection of non-net metered systems, added rules for interconnection of energy storage, added queue number assignment and utility queue reporting to the SCC, clarified the process for interdependent projects, revised the definition of "material modification," increased the upfront interconnection request study deposit for Level 3 systems, and added new forms and revised other forms.

**The definitions here cover several important classification criteria. Consult the actual rule for official definitions and additional restrictions.

Contact & resources

Please verify current program details with the administering agency before making any financial decisions.