If you install solar, wind, hydro or another qualifying system in Utah, these rules let you connect it to the utility grid. Most home solar systems fall under Level 1 if inverter-based and 25 kW or smaller, which has the simplest review, and an external disconnect switch isn't required for inverter systems of 10 kW or less. Apply through your utility, such as Rocky Mountain Power, which can explain its interconnection process and requirements.

Your customers can interconnect systems up to 20 MW under three levels based on size and complexity: Level 1 for inverter-based systems up to 25 kW, Level 2 for systems from 25 kW to 2 MW or those that fail Level 1, and Level 3 for systems up to 20 MW that don't qualify for Level 1 or 2. Systems must meet IEEE 1547 and UL 1741 and other applicable standards, and Level 2 systems connect to the distribution grid and may need an external disconnect switch. Level 3 projects may require scope, feasibility and grid impact studies, with fees billed to the customer and capped at 125% of the utility's good faith estimate.

The Utah Public Service Commission adopted these interconnection rules in April 2010, effective April 30, 2010, based on FERC Order 2006 small generator standards. They cover systems up to 20 MW in three tiers, with Level 2 having limits on single-system and aggregate grid impact and Level 3 using studies paid for by the interconnection customer. The rules apply to Rocky Mountain Power and most electric cooperatives and serve residential, commercial, industrial, agricultural, nonprofit, institutional, school and government customers using renewable and some fuel cell technologies.

Program details

Program ID
806
Last updated
6/4/2024

Eligibility

Sectors
commercial industrial local government nonprofit residential schools state government federal government agricultural institutional
Technologies
geothermal electric solar thermal electric solar photovoltaics wind (all) biomass hydroelectric hydrogen municipal solid waste fuel cells using non-renewable fuels landfill gas wind (small) hydroelectric (small) anaerobic digestion fuel cells using renewable fuels

Program summary

Utah requires the state's only investor-owned utility, Rocky Mountain Power (RMP), and most electric cooperatives* to offer net metering to customers who generate electricity using solar energy, wind energy, hydropower, hydrogen, biomass, landfill gas, geothermal energy, waste gas, or waste heat capture and recovery. The bill that established net metering also established some basic rules for interconnection. In April 2010, the Utah Public Service Commission (PSC) adopted final rules for interconnection. The rules described below took effect April 30, 2010.

Utah’s interconnection rules are based on the Federal Energy Regulatory Commission’s (FERC) interconnection standards for small generators, adopted in May 2005 by FERC Order 2006. Utah's rules for interconnection include provisions for three levels of interconnection for systems up to 20 megawatts (MW) in capacity, based on system complexity. Interconnection requirements, standards and review procedures are divided into three levels:

  • Level 1 Interconnection applies to inverter-based systems with a maximum capacity of 25 kilowatts (kW). These systems must comply with the IEEE 1547 and UL 1741 standards, and other applicable standards. An external disconnect switch is not required for inverter-based systems 10 kW or less.
  • Level 2 Interconnection applies to systems with a maximum capacity between 25 kW and 2 MW, or that fail to qualify for Level 1 interconnection. These systems also must comply with the IEEE 1547 and UL 1741 standards, and must be connected to the distribution grid. An external disconnect switch may be required. There are specific limitations on a single system's potential impact and the aggregate potential impact on the grid under Level 2 interconnection, and the review process is more involved than the review process for Level 1 interconnection.
  • Level 3 Interconnection applies to systems 20 MW or less that do not qualify for either Level 1 or Level 2 interconnection. Level 3 interconnection may require studies involving project scope, feasibility, and grid impact. Any study fees will be invoiced to the interconnection customer, but are not to exceed 125% of the utility's non-binding "good faith estimate" of the cost of the study.

The interconnection rules for Rocky Mountain Power are available here.

* Beginning in March 2008, electric cooperatives serving fewer than 1,000 customers in Utah may discontinue making net metering available to customers that are not already net metering. In addition, electric cooperatives not headquartered in Utah that serve fewer than 5,000 customers in Utah are authorized to offer net metering to their Utah customers in accordance with a tariff, schedule, or other requirement of the appropriate authority in the state in which the co-op's headquarters are located.

Contact & resources

Contact email
crevelt@utah.gov

Please verify current program details with the administering agency before making any financial decisions.