Interconnection Standards
Ohio allows you to interconnect small solar, wind, geothermal, and other distributed generation systems up to 20 MW to the grid under one of three review levels. Systems 25 kW or smaller using certified inverter equipment qualify for simplified Level 1 review, getting approval in as little as 15 business days; larger systems follow Level 2 (expedited review up to 5 MW) or Level 3 (standard review up to 20 MW) with longer timelines and potentially higher fees detailed in the rules. You can request a pre-application report for site-specific information before formally applying, though it has a cost.
Your customers' interconnection timelines and approval criteria depend on system size and equipment certification: Level 1 (≤25 kW, certified inverter-based) takes 15 business days for review; Level 2 (≤5 MW, certified inverter or synchronous) uses expedited screens; Level 3 (≤20 MW) requires standard study procedures. All applicants receive a standard interconnection agreement after approval, and utilities cannot demand additional liability insurance beyond proof of coverage. Ensure your equipment meets IEEE 1547 and UL 1741 standards for faster pathways, and consult the PUCO checklist to determine whether to file a short-form or standard application.
Ohio's interconnection framework (revised 2014) establishes three-tier review for systems up to 20 MW: Level 1 for ≤25 kW certified systems (15-day review), Level 2 for ≤5 MW with expedited technical screens, and Level 3 for larger systems requiring full study. All eligible sectors (residential, commercial, industrial, government, nonprofit) can apply; utilities must designate staff to explain requirements and offer optional pre-application reports (at applicant cost). Utilities have discretion at denial to allow interconnection if safety/reliability standards are met, require minor modifications, offer supplemental review, or move applications to Level 3, with alternative dispute resolution available for non-residential customers.
Program details
- Program ID
- 801
- Last updated
- 6/10/2024
Eligibility
- Sectors
- commercial industrial local government nonprofit residential schools state government federal government
- Technologies
- geothermal electric solar thermal electric solar photovoltaics wind (all) biomass hydroelectric municipal solid waste combined heat & power fuel cells using non-renewable fuels landfill gas wind (small) fuel cells using renewable fuels other distributed generation technologies microturbines lithium-ion
Program summary
Ohio most recently revised its interconnection rules in 2014.
Ohio's interconnection standards provide for three levels of review for the interconnection of DG systems up to 20 megawatts (MW) in capacity.
All applicants are eligible but not required to request pre-application report that provides site-specific information. Interested applicants can choose to obtain this pre-application report at a cost (request procedure, timeline and cost are detailed in 4901:1-22-04(B)(2)).
Level 1 simplified review procedure allows eligible inverter-based distributed generators to have their interconnection request reviewed within 15 business days and a standard interconnection agreement within 5 business days of determination. Key eligibility requirements for this process include a nameplate capacity of 25 kilowatts or less and meeting IEEE 1547 and UL 1741 standards. Additional, site-specific eligibility requirements and approval criteria are listed in the rules.
Level 2 interconnection has expedited and supplemental review procedures that applies to certified, inverter-based or synchronous systems up to 5 MW in capacity. Specific capacity limits vary depending upon criteria at the proposed point of interconnection. These systems must meet IEEE 1547 and UL 1741 standards and may not be interconnected at the transmission level. Technical screens, fees, capacity-limit criteria, and timelines are detailed in the rules. Approved applicants will receive a standard interconnection agreement.
If the electric distribution utility determines that the applicant does not meet the approval criteria, the utility can:
- allow the applicant to interconnect IF all safety, reliability, and power quality standards can be satisfactorily met;
- determine that further study or minor modifications must occur before the facility can meet requirements to interconnect to be carried out by either the applicant or the utility;
- obtain the applicant's agreement to continue evaluating the application under level 3 standard review;
- begin a level 2 supplemental review process described in detail in the rules
Level 3 interconnection, the standard procedure, applies to inverter-based or synchronous systems up to 20 MW in capacity that do not qualify for Level 1 or Level 2 certification. Technical screens, fees and timelines are detailed in the rules.
The interconnection forms specify two application forms for interconnection: a "short form" application for systems up to 25 kW in capacity and utilize equipment that is certified in compliance with IEEE 1547 and UL1741, and a standard application for systems that do not qualify for the "short form" application. The PUCO website also provides a checklist for applicants to determine whether to complete the "short form" or the standard form.
Each utility must provide applicants with a standard interconnection agreement following completion of project review, and must designate an employee or office to provide the applicant with information on the requirements for the utilities’ application review process. Utilities may not require additional liability insurance beyond proof of insurance. The rules include a provision for alternative dispute resolution for non-residential and non-commercial customers, and for formal complaints brought by applicants and interconnected customers. Interconnection to area networks is generally permitted but is subject to review under the 3 level review framework.