New York's Standardized Interconnection Requirements let you connect distributed generation systems up to 5 MW (including solar, wind, geothermal, fuel cells, and energy storage) to the grid across six investor-owned utilities. Systems of 50 kW or smaller qualify for an expedited six-step process with no application fee, while larger systems follow an 11-step basic process; all timelines, costs, and procedures are defined in the SIR, and utilities maintain web-based tracking of your application status. You cannot be required to purchase general liability insurance, though the state encourages you to protect yourself.

You can offer customers streamlined interconnection for systems up to 5 MW through either the expedited process (50 kW or less, or 50–300 kW with UL 1741 certified inverters) or the basic process for larger systems. Starting January 1, 2023, all new solar and storage installations must use UL 1741 SB listed inverters configured to IEEE 1547-2018 set points; energy storage projects pay a $500 plus $4/kW interconnection fee (capped at $3,000) with a 20-day utility review window. The SIR provides standard contracts and application forms, and utilities are required to offer web-based applications for systems of 25 kW or less.

New York's PSC administers the SIR for distributed generation and energy storage up to 5 MW across six investor-owned utilities (Central Hudson, Con Edison, NYSEG, National Grid, Orange and Rockland, and Rochester Gas & Electric). The program includes two stakeholder working groups (Interconnection Technical and Interconnection Policy) that develop recommendations; an Interconnection Ombudsman coordinates improvements. Utilities must publish interconnection queue data, hosting capacity maps, and web-based application systems; the SIR covers technical guidelines, application procedures, cost responsibility, and dispute resolution for all sectors including residential, commercial, industrial, agricultural, nonprofit, and government facilities.

Program details

Program ID
799
Last updated
6/7/2024

Eligibility

Sectors
commercial industrial local government nonprofit residential schools state government federal government agricultural institutional
Technologies
geothermal electric solar thermal electric solar photovoltaics wind (all) biomass hydroelectric municipal solid waste combined heat & power fuel cells using non-renewable fuels landfill gas wind (small) anaerobic digestion fuel cells using renewable fuels other distributed generation technologies microturbines lithium-ion

Program summary

New York was the second state to adopt uniform interconnection standards for distributed generation (DG) systems. The New York Public Service Commission (PSC) originally adopted Standard Interconnection Requirements (SIR) for systems up to 300 kilowatts (kW) in capacity in December 1999. The Standard Interconnection Requirements (SIR) have subsequently been amended several times since, necessitated by changing net metering rules and other legislations. Most recently, the rules were updated on January 2017 which require the developers to demonstrate that they have obtained site control while applying for interconnection. During April to December in 2016 more than 2,000 projects between 50kW and 2MW filed for interconnection leading to interconnection application backlog. This rule is designed to help clear out this backlog of inactive proposals and allow more advanced projects to be completed.

The SIR rules apply to systems up to five megawatts (MW) in capacity connected in parallel with the distribution system located in the service area of one of New York's six investor-owned local electric utilities: Central Hudson Gas and Electric, Consolidated Edison (Con Edison), New York State Electric & Gas, Niagara Mohawk (d/b/a National Grid), Orange and Rockland Utilities, and Rochester Gas and Electric. Generation facilities that are not designed to operate in parallel with the utility’s electrical systems are not subject to these requirements.

The SIR addresses technical guidelines for interconnection and application procedures, with two separate sets of interconnection procedures and processes.

Expedited Process: As amended in 2013, systems up to 50 kW are eligible for a simplified or expedited six-step process. Systems up to 300 kW may be eligible for this provided that the inverter based system is UL 1741 certified and tested. Systems proposed to be installed in underground network areas may be required to submit additional information and may subject to a longer review process. Systems of 50 kW or less are not charged an application fee.

Basic Process: This process applies to all systems larger than 50 kW up to 5 MW, and systems between 50 kW and 300 kW that have not been certified and tested in accordance with UL 1741, applicants must use the basic 11-step process for interconnection as detailed in the SIR.

Both processes cover the initial inquiry to final utility acceptance for interconnection and include interconnection timelines, responsibility for interconnection costs, and procedures for dispute resolution. The appendices contain a standard contract and standard application forms. Utilities are also required to maintain a web-based system for providing information on the status of interconnection requests to customers and contractors. The SIR contain minimum content requirements for this information system, and also require that utilities offer a web-based application process for systems of 25 kW or less.

A current list of type-tested equipment is available on the PSC's DG website. Certified, inverter-based systems up to 25 kW are not required to have an external disconnect switch. The requirements specifically state that utilities are not permitted to require customers to purchase general liability insurance; however, the PSC does encourage distributed generation owners to purchase insurance for their own protection.

Energy storage: The Standard Interconnection Requirement (SIR) was updated in October 2018 to include standards for interconnecting energy storage systems up to 5 MW AC. These standards apply to new hybrid projects, stand-alone projects, addition to energy storage system to an existing distributed generation facility, and changing of operating mode of existing hybrid or stand alone facility. Interconnection fee is calculated at $500 plus $4/kW capped at $3,000. The utility will have 20 days to perform the review and provide any modifications for control systems deemed necessary. The design of the system must include automatic disconnect device that will disconnect from the grid in case of power outage.

Smart inverters: Starting January 1st 2023, utilities in NY will increasingly require all new solar and storage installations be configured to their preferred IEEE 1547-2018 set points. In addition, the New York State Standardized Interconnection Requirements document (NYS SIR) will be modified to require the use of UL 1741 SB listed inverters.

Contact & resources

Please verify current program details with the administering agency before making any financial decisions.