Interconnection Standards
California's Rule 21 interconnection standard allows you to connect qualifying distributed generation systems (such as solar, wind, or fuel cells) to your utility's grid while protecting system safety and reliability. Most net-metered systems and non-exporting (on-site use only) systems qualify for fast-track approval without extensive fees, while larger exporting systems may require supplemental or detailed review—contact your specific utility (PG&E, SCE, SDG&E, or your municipal utility) for their interconnection tariff and application process.
Rule 21 establishes standardized interconnection pathways across California's investor-owned utilities, with fast-track eligibility for net-metered systems and non-exporting facilities, and detailed study processes for larger exporting systems. You must apply through the customer's utility and follow that utility's specific version of Rule 21, which includes initial review screens, fixed timelines, and various fees and deposits depending on project size and export capability; net-metered facilities are exempt from most fees.
Rule 21, adopted in 1982 and revised through ongoing rulemakings (most recently R.25-08-004), establishes interconnection requirements for all distributed generation facilities connecting to California's seven investor-owned utilities' distribution and transmission systems. The tariff uses tiered screening (initial review, fast-track, supplemental review, and detailed study processes) to allocate projects efficiently, with each utility administering its own Rule 21 version; PacifiCorp follows FERC-compliant OATT standards. Current administration is managed by CPUC with stakeholder input through the Interconnection Discussion Forum and Smart Inverter Working Group.
Program details
- Program ID
- 779
- Last updated
- 6/4/2024
Eligibility
- Sectors
- commercial industrial residential
- Technologies
- geothermal electric solar thermal electric solar photovoltaics wind (all) biomass hydroelectric municipal solid waste combined heat & power fuel cells using non-renewable fuels landfill gas wind (small) fuel cells using renewable fuels other distributed generation technologies microturbines
Program summary
Note: The California Public Utilities Commission (CPUC) has an ongoing interconnection rule revision docket (Rulemaking (R.) 17-07-007) that has made many revisions to interconnection rules since July 13, 2017. Current interconnection rules for each utility are available at the CPUC website.
California's "Rule 21" generally applies to systems connecting to an investor-owned utility’s distribution grid, non-export generating facilities connecting to an investor-owned utility’s transmission grid and all net metered facilities in an investor-owned utility’s service territory. Systems connecting to an investor-owned utility’s distribution grid for the purpose of participating in a wholesale transaction must apply under the investor-owned utility’s Wholesale Distribution Access Tariff. Systems connecting to the transmission grid must apply to the California Independent System Operator for interconnection. Systems connecting to the grid of a municipal or cooperative utility must follow the interconnection procedures adopted by that utility.
Rule 21 clearly defines a series of screens meant to filter applicants into the study path most suited for their project. It also establishes fixed timelines for the screens intended to speed the process of approval. Also defined in the tariff are a variety of fees and deposits required at various stages of the interconnection process. Net metered facilities are exempt from most of these fees.
Fast Track Eligibility
Non-exporting systems (sized and designed so that the electricity is only used on-site and will never deliver electricity to the grid) and all net metered systems, regardless of nameplate capacity, can qualify for Fast Track. Exporting facilities may also be considered for Fast Track if they meet certain size restrictions or if the owner agrees to certain utility-approved protective devices.
After a customer applies for interconnection, the utility performs an Initial Review. If the applicant passes through Initial Review, the system will be able to interconnect without a Supplemental Review. If Supplemental Review is required, the applicant will be notified and can elect to have their application withdrawn, or proceed through the next layer of screens.
Detailed Study Eligibility
Systems not eligible for Fast Track may apply for interconnection through a detailed study process. The detailed study options include an Independent Study Process, a Distribution Group Study Process or a Transmission Cluster Study Process. The parameters for each process are provided in Rule 21.