Interconnection Standards
If you install solar or other small generation with a Duke Energy Progress, Duke Energy Carolinas, or Dominion North Carolina Power connection, systems up to 20 kW use the simplest inverter process with a $100 application fee. Utilities can't require residential customers to carry more liability insurance than a standard homeowner's policy ($100,000 minimum), and they must reimburse the cost of any required external disconnect switch for systems under 10 kW. These rules don't cover municipal utilities or electric co-ops, so check with them or your utility's interconnection page to apply.
Your customers with investor-owned utility service get a three-tier process: Inverter (up to 20 kW), Fast Track (over 20 kW if voltage and size criteria are met), and Study for everything else, with Study requiring a $20,000 deposit plus $1 per kW-AC, capped at $100,000. Application fees are $100 up to 20 kW, $750 above 20 kW to 100 kW, and $1,000 above 100 kW to 2 MW, plus $500 for a pre-application report, and non-residential systems need $300,000 (up to 250 kW) or $1,000,000 (over 250 kW) in liability insurance unless they qualify to self-insure. Agreements don't transfer, so new owners file a request with a $50 fee without re-study, and adding storage or DC equipment to existing PV that doesn't change capacity, production profile, or AC configuration isn't a material modification and avoids re-entering the queue.
The NCUC adopted these standards in 2005, updated them in 2008 and 2015, and revised them by a June 2019 order that added storage provisions for existing solar PV and expedited review of swine and poultry waste projects of 2 MW or less under HB 589. They are modeled on FERC's small generator procedures, apply to Duke Energy Progress, Duke Energy Carolinas, and Dominion North Carolina Power regardless of generator size or whether power is sold or self-consumed, and exclude municipal utilities and cooperatives. Fees are paid by applicants on a tiered schedule with FERC's structure applying above 2 MW, and the rules cover residential, commercial, industrial, agricultural, government, nonprofit, and institutional customers across a wide range of distributed technologies.
Program details
- Program ID
- 354
- Last updated
- 6/7/2024
Eligibility
- Sectors
- commercial industrial local government nonprofit residential schools state government federal government agricultural institutional
- Technologies
- solar thermal electric solar photovoltaics wind (all) biomass municipal solid waste combined heat & power fuel cells using non-renewable fuels landfill gas wind (small) hydroelectric (small) anaerobic digestion fuel cells using renewable fuels other distributed generation technologies microturbines lithium-ion
Program summary
Note: HB 589, signed in July 2017, requires the NCUC to adopt an expedited review process for swine and poultry waste energy projects of 2 MW or less. The NCUC issued an order in June 2019 with revisions to the interconnection standard including provisions for adding energy storage at existing solar PV sites, and expedited study of interconnection standard for small swine and poultry waste facilities.
The North Carolina Utilities Commission (NCUC) first adopted comprehensive interconnection standards for distributed generation in 2005. The NCUC later updated the interconnection standards in 2008 and 2015. The current NCUC standards, which are similar to the Federal Energy Regulatory Commission’s (FERC) interconnection standards for small generators, govern interconnection to the distribution systems of the state's three investor-owned utilities: Duke Energy Progress, Duke Energy Carolinas, and Dominion North Carolina Power.* The standards apply to all state-jurisdictional interconnections (including interconnection of three-phase generators) regardless of the capacity of the generator, the voltage level of the interconnection, or whether the customer intends to offset electricity consumption or sell electricity.
Size Criteria
The NCUC standards, like the FERC standards, use a three-tiered approach to simplify the interconnection process:
- Inverter Process: Systems up to 20 kilowatts (kW)
- Fast Track Process: Systems larger than 20 kW that meet the eligibility criteria in the table below
- Study Process: Systems that fail to qualify for the Fast Track Process
| Line Voltage | Fast Track Eligible Regardless of Location | Fast Track Eligibility on a Mainline and less than 2.5 Electrical Circuit Miles from Substation |
| Less than 5 kV | Less than or equal to 100 kW | Less than or equal to 500 kW |
| Between 5 kV and 15 kV | Less than or equal to 1 MW | Less than or equal to 2 MW |
| Between 15 kV and 35 kV | Less than or equal to 2 MW | Less than or equal to 2 MW |
| Greater than or equal to 35 kV | Not eligible | Not eligible |
External Disconnect SwitchUtilities are authorized to require an external disconnect switch, but must reimburse owners of systems smaller than 10kW for the cost of the switch. Interconnection agreements are not transferrable; new owners must secure an agreement by filing an interconnection request and submitting a fee of $50. (However, the interconnection will not need to be re-studied.) The standards include a provision for mutual indemnification and a weak process for dispute resolution.
Fees
The NCUC established a fee structure for interconnection applications: $500 for filing a pre-applicaiton report request; $100 for generators up to 20 kW; $750 for generators larger than 20 kW but not larger than 100 kW; and $1000 for generators larger than 100 kW but not larger than to 2 MW. The FERC fee structure applies to the interconnection of systems over 2 MW. Additionally, systems in the Study Process must pay a deposit of $20,000, plus $1 per kW-AC, not to exceed $100,000.
Addition of Energy Storage
Existing solar PV systems can be upgraded in the DC system that does not impact the maximum generation capacity, daily production profile, or the proposed AC configuration of the generation facility including- DC optimizers, DC-DC converters, DC charge controllers, power plant controllers, and energy storage devices that the output is delivered during the same periods and with the same profile considered during the System Impact study- will not be considered a material modification and will not need to re-enter the interconnection queue. Other changes to the system might be considered as material modification to the system, and be required to re-enter the interconnection queue.
Click here for Duke Energy Carolinas' website for interconnection, or here for Duke Energy Progress's, website for interconnection.
*The NCUC’s interconnection standards do not govern interconnection to municipal utilities or electric cooperatives.
History
Legislation enacted by North Carolina in August 2007 (S.B. 3) required the NCUC to establish interconnection standards for distributed generation systems up to 10 MW in capacity. The law stated that the commission “shall adopt, if appropriate, federal interconnection standards.” This law also established North Carolina’s Renewable Energy and Energy Efficiency Portfolio Standard (REPS).